A project manager is giving a project update to the key stakeholders. During the meeting, he finds out that most of the stakeholders are busy checking and replying to their emails. Which of the following is the best action that could have eliminated this issue? A. A meeting ground rule on active listeningB. Providing snacks
PMP Exam Set C – Q31
You are authorized to approve expenditures above $15,000. For the last several weeks you have been negotiating the terms and pricing of a contract with a vendor, and you want to keep costs as low as possible. This has been a very difficult negotiation process. A colleague suggests you tell the vendor you can only
PMP Exam Set C – Q30 ( PMBOK 6th edition )
As part of the Control Procurements process, the project manager prepared a complete set of indexed contract documentation, including the closed contract, to include with the final project files. This is called a: A. Procurement fileB. Documentation fileC. Closure reportD. Closure file Show Answer A. Procurement file
PMP Exam Set C – Q29
What does it mean if the Earned Value is equal to Actual Cost? A. Schedule Variance Index is 1B. Project is on budget and on scheduleC. There is no cost varianceD. There is no schedule variance Show Answer C. There is no cost variance
PMP Exam Set C – Q28
Decision making is an important skill a project manager must possess to manage and lead the team. Which of the following is NOT a part of the six- phase decision-making model? A. Solution evaluation planningB. Solution action planningC. Problem solution generationD. Problem solution escalation Show Answer D. Problem solution escalation
PMP Exam Set C – Q27 ( PMBOK 6th edition )
Which of the following activities fall under the planning process group but not under the Project Schedule Management? A. Estimating the type of materials and equipment needed to perform project activitiesB. Developing the Schedule Management PlanC. Identification of various activities to produce the project deliverablesD. Developing a detailed description of the project and product being
PMP Exam Set C – Q26
While going through a list of candidates to be hired for your project, you find that your cousin is one the 3 short listed candidates. You know that she was desperately looking for job. After reviewing these resumes, you’ll be sending them to the electronics engineer for a technical interview. Having a first look at
PMP Exam Set C – Q25
A good quality audit should be: A. structured and independentB. informal and independentC. informal and internalD. structured and internal Show Answer A. structured and independent
PMP Exam Set C – Q24
All of the monitoring and control processes and many of the executing processes produce change requests as an output. Change requests include corrective action and preventive action. Which of the following are normally affected by corrective and preventive actions? A. Defect repairB. Regressive baselinesC. The project baselinesD. The performance against baselines Show Answer D. The
PMP Exam Set C – Q23
A project manager has decided to use a decision tree to make a build or upgrade analysis. The build requires an investment of $ 200 M (where M represents million). On the build decision branch, there is a 60% probability of strong demand (yielding a revenue of $ 400 M) and a 40% probability of