PMP Exam Set C – Q32

A project manager is giving a project update to the key stakeholders. During the meeting, he finds out that most of the stakeholders are busy checking and replying to their emails. Which of the following is the best action that could have eliminated this issue? A. A meeting ground rule on active listeningB. Providing snacks

PMP Exam Set C – Q31

You are authorized to approve expenditures above $15,000. For the last several weeks you have been negotiating the terms and pricing of a contract with a vendor, and you want to keep costs as low as possible. This has been a very difficult negotiation process. A colleague suggests you tell the vendor you can only

PMP Exam Set C – Q28

Decision making is an important skill a project manager must possess to manage and lead the team. Which of the following is NOT a part of the six- phase decision-making model? A. Solution evaluation planningB. Solution action planningC. Problem solution generationD. Problem solution escalation Show Answer D. Problem solution escalation

PMP Exam Set C – Q27 ( PMBOK 6th edition )

Which of the following activities fall under the planning process group but not under the Project Schedule Management? A. Estimating the type of materials and equipment needed to perform project activitiesB. Developing the Schedule Management PlanC. Identification of various activities to produce the project deliverablesD. Developing a detailed description of the project and product being

PMP Exam Set C – Q26

While going through a list of candidates to be hired for your project, you find that your cousin is one the 3 short listed candidates. You know that she was desperately looking for job. After reviewing these resumes, you’ll be sending them to the electronics engineer for a technical interview. Having a first look at

PMP Exam Set C – Q25

A good quality audit should be: A. structured and independentB. informal and independentC. informal and internalD. structured and internal Show Answer A. structured and independent

PMP Exam Set C – Q24

All of the monitoring and control processes and many of the executing processes produce change requests as an output. Change requests include corrective action and preventive action. Which of the following are normally affected by corrective and preventive actions? A. Defect repairB. Regressive baselinesC. The project baselinesD. The performance against baselines Show Answer D. The

PMP Exam Set C – Q23

A project manager has decided to use a decision tree to make a build or upgrade analysis. The build requires an investment of $ 200 M (where M represents million). On the build decision branch, there is a 60% probability of strong demand (yielding a revenue of $ 400 M) and a 40% probability of