A seller entered into contract with a buyer. At the end of the project, the seller was reimbursed for the cost of the project, but received a very low fee based on certain subjective criteria that had been laid down in the contract. What type of contract is this likely to be? A. Cost Plus
PMP Exam Set C – Q21
You are attempting to estimate the resources required to put the server racks together in the new data center you are building. It has occurred to you that you may be able to compress the schedule if you look at using power tools vs. hand tools to build the racks and use individuals who have
PMP Exam Set C – Q20
____________ is performed on risks that have been prioritized by the Perform Qualitative Risk Analysis process as potentially and substantially impacting the project. A. Perform Risk Cost AnalysisB. Perform Risk Exposure AnalysisC. Perform Quantitative Risk AnalysisD. Perform Risk Outcome Analysis Show Answer C. Perform Quantitative Risk Analysis
PMP Exam Set C – Q19
A project manager wants to understand a project goal in relation to the steps for getting to that goal. Which of the following is a useful method for contingency planning that aids a team in anticipating intermediate steps that could derail achievement of a project goal? A. Affinity diagramB. Process decision program charts (PDPC)C. Interrelationship
PMP Exam Set C – Q18
You are working on a data center migration project and will be moving a mainframe system to another data center. However, you can’t have any downtime when performing the move. The subject matter experts have various ideas regarding how this daunting task can be done, but the group is not coming to a consensus. You
PMP Exam Set C – Q17
A project manager manages a distributed team with team members located in five countries. Due to time-zone differences, he is unable to find a time that is acceptable to all team members. Which conflict resolution technique is best suited for this situation? A. CompromiseB. ForceC. WithdrawD. Avoid Show Answer A. Compromise
PMP Exam Set C – Q16
A first-time project manager was assigned to a project that had a duration of 3 months. In order to gain a head start in the project, she took an older, completed project and incorporated all the tools, techniques and checklists from that project in their entirety into the current one. The older project had been
PMP Exam Set C – Q15
What do buyers and seller have in common with regards to Control Procurements? A. Each party ensures that both it and the other party meet their contractual obligations and that their own legal rights are protected.B. Both parties have specific resources that can be idle.C. Both parties have a contract change management plan.D. Each party
PMP Exam Set C – Q14
Which of the following is not true about the WBS? A. The project team must be involved in developing the WBSB. The WBS must represent all product and project work.C. WBS should focus on activities rather than deliverablesD. WBS is usually represented in a hierarchical fashion Show Answer C. WBS should focus on activities rather
PMP Exam Set C – Q13
You are involved as project manager in a fairly large-sized project. You are in the process of making a procurement decision and plan to go with a simple purchase order. However, you are doubtful whether this is the correct thing to do and decide to find out more details about the process to be followed.