PMP Exam Set E – Q21

You are managing a project with a large multi-national staff. One of the engineers was originally tasked to deliver her part of the work on Oct 19, but due to the change in the critical path, her deliverable will be needed 2 days sooner. However, as the new deadline is still 2 weeks away and

PMP Exam Set E – Q20

The sponsor and the project manager are discussing what type of contract the project manager plans to use on the project. The buyer points out that the performing organization spent a lot of money hiring a design team to come up with the design. The project manager is interested in seeing that the risk for

PMP Exam Set E – Q19

You have been asked to fill in for another project manager while he is on vacation. During the next project status meeting, you ask for a risk report. The project team says they have never reported on that before, and are unsure if there is a master project risk log. What do you do? A.

PMP Exam Set E – Q18

Which of the following contains an extensive procurement changes approval process? A. Scope statementB. Test planC. Requirements management planD. Contract change control system Show Answer D. Contract change control system

PMP Exam Set E – Q17

John is managing a computer network deployment project at a university campus. John wants to involve the key project stakeholders in the scheduling of the major work packages. He sends out a meeting invitation to all key stakeholders for this brainstorming session. Which of the following types of communication methods has John selected for the

PMP Exam Set E – Q16

Which of the following is considered an output from the Direct and Manage Project Work process? A. Budgeted costsB. Project charterC. Work performance dataD. Execution plan Show Answer C. Work performance data

PMP Exam Set E – Q15

The Cost of Quality principle includes: _______________ A. The costs of ensuring conformance to requirements.B. The costs involved when changes are made to the requirements.C. The cost of deploying a project Configuration Management SystemD. The costs associated with eliminating requirements. Show Answer A. The costs of ensuring conformance to requirements.

PMP Exam Set E – Q14

A control chart should always contain: ______________ A. Upper and lower warning limitsB. The moving averageC. Upper and lower control limitsD. Upper and lower specification limits Show Answer C. Upper and lower control limits

PMP Exam Set E – Q13

The Project Charter formally authorizes a project. Who authorizes the project charter? A. The project managerB. A project sponsor or initiator internal to the projectC. The user of the productD. A project sponsor or initiator external to the project Show Answer D. A project sponsor or initiator external to the project