PMP Exam Set E – Q12

Probability distributions are frequently used in Perform Quantitative Risk Analysis. Which of these is not a valid example of such a distribution? A. Sigma distributionB. Logarithmic distributionC. Triangular distributionD. Beta distribution Show Answer A. Sigma distribution

PMP Exam Set E – Q10

Which of the following statements is incorrect? A. Developing project team is the responsibility of the project manager.B. A project manager must not acquire resources needed to develop effective project teams.C. High team performance can be achieved using open and effective communications.D. Teamwork is a critical success factor for a project. Show Answer B. A

PMP Exam Set E – Q9

A project manager found that some of the project work was not done at the right time and was done in an improper sequence. What do you think was the likely issue? A. This is a project communications breakdown. The project manager needs to re-develop the communication management planB. The Project Scope document was not

PMP Exam Set E – Q8

A project team is currently inspecting the recent project deliverables. The team is recording the number and the nature of defects found in these deliverables. The defect details list in this case is an example of? A. Quality control checklistB. Work performance dataC. Change requestD. Work performance information Show Answer B. Work performance data

PMP Exam Set E – Q7

The number of communication channels depends on the number of team members in any project. If five team members are released from a team of 25, how many communication channels remain in the project? A. 300B. 625C. 190D. 400 Show Answer C. 190

PMP Exam Set E – Q6

Which of the following statements accurately describes how the completion of project scope and product scope is measured? A. The completion of project scope and product scope are both measured against the product requirements.B. The completion of project scope is measured against the project management plan whereas the completion of product scope is measured against

PMP Exam Set E – Q5

You have completed your estimates for your project and determined that it will take 10 months to complete. However, your project sponsor insists that it be completed in 9 months. How do you handle this? A. Increase the budget by 10%B. Inform the sponsor you will have to explore the options before committing to that

PMP Exam Set E – Q4

For your weekly project status review meetings, you set some time aside on the agenda to review the risk register and review the project risks. You ensure that the response plans are still appropriate and add or delete risks as necessary. This is an example of? A. Technical Performance MeasurementB. Trend AnalysisC. Risk ReassessmentD. Risk

PMP Exam Set E – Q3

The paint on the exotic cars that are manufactured in your plant is bubbling after about a year of application. What would be the BEST tool for your team to use to find potential causes of the peeling paint? A. Defect Repair ReviewB. Ishikawa DiagramC. Control ChartD. Inspection Show Answer B. Ishikawa Diagram