The State of New York has contracted your company to provide a claims payment system for Medicaid benefits. In the contract there is a clause that indicates that the State of New York can review your work processes and deliverables. This is an example of? A. Performance ReportB. Record Management SystemC. Deliverables ChecklistD. Inspections and
PMP Exam Set C – Q81
As the Project Manager on the construction of a new hotel you have developed a project management plan that you believe is realistic and will be formally approved. The organizational assets that influenced the development of the plan may include all of the following except: A. Project management plan templatesB. Risk register from a past
PMP Exam Set C – Q80
The Work Breakdown Structure (WBS) is a deliverable-oriented hierarchical decomposition of the work to be executed by the project team, to accomplish the project objectives and create required deliverables. The ‘Create WBS’ is a process under which Knowledge Area? A. Project Schedule ManagementB. Project Integration Management.C. Project Scope ManagementD. Project Cost Management Show Answer C.
PMP Exam Set C – Q79
An organization wishes to ensure that the opportunity arising from a risk with positive impact is realized. This organization should: A. Exploit the riskB. Mitigate the riskC. Accept the riskD. Avoid the risk Show Answer A. Exploit the risk
PMP Exam Set C – Q78 ( PMBOK 6th edition )
A project management team came up with certain metrics such as defect frequency, failure rate, availability and reliability. These are usually defined as an output of what process? A. Plan Quality ManagementB. Define ScopeC. Collect RequirementsD. Manage Quality Show Answer A. Plan Quality Management
PMP Exam Set C – Q77 ( PMBOK 6th edition )
Accepted deliverables are an input to the Close Project or Phase process. These deliverables would have been accepted through which of the following processes? A. Validate ScopeB. Control QualityC. Control ScopeD. Manage Quality Show Answer A. Validate Scope
PMP Exam Set C – Q76
A Resource Breakdown Structure (RBS) would be used to breakdown the project by type of resources. The RBS is an example of a: A. Linear chartB. Matrix chartC. Flow chartD. Hierarchical chart Show Answer D. Hierarchical chart
PMP Exam Set C – Q75
You are a consulting project manager with over 15 years experience running software development projects. You have been engaged to manage a finance application project for a new customer. However on the first day onsite at the customer’s headquarters you are told the project has been cancelled, but there is a need for a project
PMP Exam Set C – Q74
Midway through the Collect Requirements process, a project manager finds that there are lots of unresolved issues. Which of the following is usually the best way to discover and resolve issues? A. InterviewingB. Use of a stakeholder registerC. QuestionnairesD. Facilitated workshops Show Answer D. Facilitated workshops
PMP Exam Set C – Q73
Which of these items are important to address when determining each person’s role in the project team? A. Role, authority, responsibility, and competencyB. Role, responsibility, and competencyC. Role and responsibilityD. Role, authority, and competency Show Answer A. Role, authority, responsibility, and competency