You have been asked by your project manager to help them create a chart that illustrates the project resources that will be working on each work package. What would be the best type of chart to use? A. Milestone chartB. RACI chartC. Project organization chartD. WBS Show Answer B. RACI chart
PMP Exam Set C – Q61
Which of the following statements most accurately describes a project scenario? A. Changes in project scope during the initial phases of the project are very expensive.B. The influence of the stakeholders is the same all through the project.C. Staffing peaks up during the execution phase of a project.D. The next phase of a project should
PMP Exam Set C – Q60
A company you worked for several years ago is bidding on a project your new company will be starting in approximately 6 months. You have been selected to manage the project, and will be participating in the vendor selection processes. What should you do? A. Notify the stakeholders of your status and excuse yourself from
PMP Exam Set C – Q59
Richard is currently assessing his project stakeholders influences, interests, expectations, risk tolerance and engagement levels. This relates to which of the following tools and techniques? A. Stakeholder registerB. Stakeholder analysisC. Autocratic decision makingD. Expert judgement Show Answer B. Stakeholder analysis
PMP Exam Set C – Q58
You are setting up your project team and you are looking at a chart that shows that the programming will be performed by Systems Development, the infrastructure will be implemented by Infrastructure Systems, the customer communication will be handled by the Call Center. This is an example of what type of chart? A. RACIB. Organizational
PMP Exam Set C – Q57
Experienced project managers always tell that accuracy and precision are not the same. Precise measurements may not be accurate and accurate measurements may not be precise. Which of the following statementsabout the precision and accuracy are CORRECT? A. Accuracy means the degree to which a set of inherent characteristics fulfill requirements and Precision means a
PMP Exam Set C – Q56
Peter is managing the development of an ecommerce website for his organization. Peter enjoys coercive powers and has assigned Julie, a project team member, to facilitate the team meetings. During any team meeting, Julie must? A. Influence team members to support the project manager’s decisionsB. Support the team members to challenge the project manager’s decisionsC.
PMP Exam Set C – Q55
The RACI chart is an example for a responsibility assignment matrix (RAM). The letters R and C in RACI chart stand for A. Responsible and consultB. Resource and consultantC. Responsible and categorizeD. Resource and consult Show Answer A. Responsible and consult
PMP Exam Set C – Q54
You have been offered a position managing a project that will last 12 months. However, you know that in 6 months you will be relocating to another state for family reasons. What should you do? A. Turn down the position.B. Accept the position and provide 4 weeks notice before leaving the job.C. Accept the position
PMP Exam Set C – Q53
A project manager is performing a set of processes in the Initiating Process Group. Which of the following is likely to be part of the Initiating Process Group? A. Develop Project Management PlanB. Define ScopeC. Develop Project CharterD. Plan Quality Management Show Answer C. Develop Project Charter