PMP Exam Set G – Q52

The product design your project team developed was very well received by the customer. There were two key contributors to this design. The customer calls you to tell you how pleased he is with the design. What do you tell him? A. Ask to negotiate a bonus payment.B. Thank the customer.C. Thank him on behalf

PMP Exam Set G – Q50

Peter works as a project manager for GOODSTEEL, a steel melting shop. He was assigned by his Executive Project Manager to study and prepare a report on the defects that eroded the blast furnace lining which has caused a drastic decline in production. Since this report will be used by the management to control the

PMP Exam Set G – Q47

The morale of the team members of a project is very low. The team members feel that they were not given opportunities to participate in the organizational team development activities due to over allocations to project tasks, and hence they missed opportunities to grow. Which of the following is a primary factor for this situation?

PMP Exam Set G – Q46

Calculation of late finish dates and late start dates for the uncompleted portion of the project is called . A. Schedule compressionB. An arrow diagramC. A backward passD. A forward pass Show Answer C. A backward pass

PMP Exam Set G – Q44

You have been managing a construction project in a developing country and are closing down the project. The tools and equipment that was used on the project has to be returned to your company’s European headquarters. A non-governmental organization that builds and repairs medical facilities in this country has come to you to request that

PMP Exam Set G – Q43

All of the following activities are performed in the Close Project or Phase process EXCEPT A. Activities that fulfill the exit criteria of the projectB. Sending the deliverables to the customer for acceptanceC. Activities which are needed to transfer the completed products to operationsD. Documenting the reasons for projects terminated early Show Answer B. Sending