The product design your project team developed was very well received by the customer. There were two key contributors to this design. The customer calls you to tell you how pleased he is with the design. What do you tell him? A. Ask to negotiate a bonus payment.B. Thank the customer.C. Thank him on behalf
PMP Exam Set G – Q51
You are managing a project for a customer that has just gone bankrupt and is subject to liquidation proceedings. There are several outstanding invoices that this customer has not paid to your company. What should you do now? A. Go into alternate dispute resolutionB. Do nothing.C. Contact the appropriate management at your company for advice
PMP Exam Set G – Q50
Peter works as a project manager for GOODSTEEL, a steel melting shop. He was assigned by his Executive Project Manager to study and prepare a report on the defects that eroded the blast furnace lining which has caused a drastic decline in production. Since this report will be used by the management to control the
PMP Exam Set G – Q49
The Identify Stakeholders process is an initiating process. At this stage, which of the following organizational process assets is the most crucial input to this process? A. Change control proceduresB. Lessons learned from previous projects.C. Financial control proceduresD. Risk control procedures Show Answer B. Lessons learned from previous projects.
PMP Exam Set G – Q48 ( PMBOK 6th edition )
You have been chosen by a program management office (PMO) to write a purchase order for your expertise in business writing. You have learned that the PMO has already selected a seller for a software product and would like to award the procurement contract to the selected seller as a purchase order which you must
PMP Exam Set G – Q47
The morale of the team members of a project is very low. The team members feel that they were not given opportunities to participate in the organizational team development activities due to over allocations to project tasks, and hence they missed opportunities to grow. Which of the following is a primary factor for this situation?
PMP Exam Set G – Q46
Calculation of late finish dates and late start dates for the uncompleted portion of the project is called . A. Schedule compressionB. An arrow diagramC. A backward passD. A forward pass Show Answer C. A backward pass
PMP Exam Set G – Q45
You are a Project Manager working on a project to create safe electric motors for Tessla introducing a new electric car. Your company’s president is keenly interested in the project and requests a chart that shows the number of defects by type ordered by their frequency of occurrence. Which type of chart would BEST meet
PMP Exam Set G – Q44
You have been managing a construction project in a developing country and are closing down the project. The tools and equipment that was used on the project has to be returned to your company’s European headquarters. A non-governmental organization that builds and repairs medical facilities in this country has come to you to request that
PMP Exam Set G – Q43
All of the following activities are performed in the Close Project or Phase process EXCEPT A. Activities that fulfill the exit criteria of the projectB. Sending the deliverables to the customer for acceptanceC. Activities which are needed to transfer the completed products to operationsD. Documenting the reasons for projects terminated early Show Answer B. Sending