PMP Exam Set G – Q42

You are working for GOODROAD highway construction agency as a project cost estimator. The agency started a highway construction project which is in it’s planning phase. The rough order of magnitude (ROM) cost estimate for the project is expected to be between 3 and 5 million dollars in the planning phase with a ROM of

PMP Exam Set G – Q41

John, a project manager, is a certified PMP. He is responding to an RFP from a buyer and needs to fill in details on the financial performance of his company. His company has performed badly during the current quarter and the results will be published in 2 to 3 days’ time. However, the company has

PMP Exam Set G – Q40

In a sender-receiver model for communication, information is sent and received between two parties, defined as the sender and the receiver. In such a model, anything that interferes with the transmission and understanding of the message is called: A. NoiseB. ConstraintC. MediumD. Decode Show Answer A. Noise

PMP Exam Set G – Q39

In a matrix organization, where the team members report to both, a functional manager as well as a project manager, generally, whose responsibility is it to manage the dual reporting relationship? A. Functional managerB. HR managerC. Team membersD. Project Manager Show Answer D. Project Manager

PMP Exam Set G – Q38

A manager asks you to evaluate four new projects that he has suggested for next year. You review the projects and notice that one is not really a project, but more an operational task. Which of these is not a project? A. Change the product to enable increased consumer usageB. Manage a set of people

PMP Exam Set G – Q37

When beginning a new outsourcing project, what is the best way to determine which companies you should request a bid from? A. Send your proposal to the company you last worked withB. Have someone else manage this part of the processC. Send your proposal to everyoneD. Consult the qualified sellers list Show Answer D. Consult

PMP Exam Set G – Q36 ( PMBOK 6th edition )

A project manager is currently ensuring that the stakeholders clearly understand the project goals, objectives, benefits and risks. This relates to which of the following processes? A. Monitor Stakeholder EngagementB. Identify StakeholdersC. Plan Communications ManagementD. Manage Stakeholder Engagement Show Answer D. Manage Stakeholder Engagement

PMP Exam Set G – Q35

A project manager would find team development to be the MOST difficult in which type of organization? A. Functional organizationB. Projectized organizationC. Weak matrix organizationD. Balanced matrix organization Show Answer A. Functional organization

PMP Exam Set G – Q34

You are the project manager from a seller organization, based at the customer location. One of your team members is involved in certain unacceptable activities at the customer location. The HR manager of the customer team organizes a meeting between you, the team-member, your customer- manager and HR wherein the team member apologizes for his

PMP Exam Set G – Q33

If you want to reduce the number of quality inspections and thus reduce the cost of quality control for your project, which technique should be used? A. Run ChartB. Defect Repair ReviewC. Statistical SamplingD. Pareto Chart Show Answer C. Statistical Sampling