What is the MAIN reason for controlling the project scope? A. To enable scope creepB. To prevent changes from affecting the projectC. To ensure timely closure of the project.D. Preventing scope creep. Show Answer D. Preventing scope creep.
PMP Exam Set A – Q71
You are in the Validate Scope process of your electronic goods manufacturing project. While reviewing some products, you have noticed that the tolerance for one product is 0.01% less than what was listed in the requirements documentation. This deviation may not be a problem for the customers and it may not negatively impact the operations.
PMP Exam Set A – Q70
As part of the Define Scope process, a project manager documented the specific project assumptions associated with the project scope in the project scope statement. While reviewing this document, an experienced project manager pointed out that the project manager should also document: A. The date on which the assumption becomes invalid.B. The assigned responsibility for
PMP Exam Set A – Q69
What is the traditional way to display a reporting structure among project team members? A. Text-oriented role descriptionB. FlowchartC. Hierarchical-type chartsD. Matrix based responsibility chart Show Answer C. Hierarchical-type charts
PMP Exam Set A – Q68 ( PMBOK 6th edition )
The Manage Team process is part of what process group? A. PlanningB. ExecutingC. Monitoring and ControllingD. Closing Show Answer B. Executing
PMP Exam Set A – Q67
A Project manager estimates the work to be accomplished in the near term in detail, at a low level of the Work Breakdown structure (WBS); while he estimates work far in the future as WBS components, that are at a relatively high level of the WBS. What is this technique called? A. DecompositionB. Rolling wave
PMP Exam Set A – Q66
Your company has temporarily assigned you to serve as a project manager at a company location outside your home country. While meeting with a vendor your first day on the job, you are presented with a gift. The corporate policy at the headquarters in your home country prohibits employees from accepting these types of gifts.
PMP Exam Set A – Q65
A large network hardware upgrade project was scheduled to take place over a weekend. During the course of the implementation, several previously unidentified dependencies for additional materials were discovered. The project manager gave approval for the tech staff doing the implementation procure with corporate credit cards several hundred dollars worth of additional equipment required to
PMP Exam Set A – Q64
Risk identification checklists are usually developed based on historical information and knowledge accumulated from previous similar projects. Which of the following statements about risk identification checklists is wrong? A. It is impossible to build an exhaustive checklist.B. The lowest level of the Risk Breakdown Structure (RBS) cannot be used as a risk checklistC. Quick and
PMP Exam Set A – Q63
While developing the project schedule, you find that the completion of a successor activity depends on the completion of its predecessor activity. What is this dependency called? A. Start-to-FinishB. Start-to-StartC. Finish-to-StartD. Finish-to-Finish Show Answer D. Finish-to-Finish