Which of the following enterprise environmental factors is not applicable to the Plan Resource Management process? A. Organizational culture and structureB. Existing human resourcesC. Personnel administration policiesD. Lessons learned Show Answer D. Lessons learned
PMP Exam Set A – Q61
The Project Managers have maximum authority in which type of organization? A. Weak MatrixB. Strong MatrixC. FunctionalD. Balanced Matrix Show Answer B. Strong Matrix
PMP Exam Set A – Q60
John has just been assigned as the project manager of a project to develop a complex product. The project is in the Define Scope phase. Which of these tools / techniques will not be used by John in this phase? A. Lateral thinkingB. Process analysisC. Product breakdownD. Value engineering Show Answer B. Process analysis
PMP Exam Set A – Q59
Collect Requirements, Develop Schedule and Perform Qualitative Risk Analysis are all part of what process group? A. PlanningB. Scope PlanningC. Monitor and ControllingD. Executing Show Answer A. Planning
PMP Exam Set A – Q58
Which strategy attempts to reduce the probability and/or the impact of a risk to the point where the risk can be accepted? A. MitigationB. AvoidanceC. AcceptanceD. Transfer Show Answer A. Mitigation
PMP Exam Set A – Q57
How can changes be made to a project management plan once it has been baselined by the project manager? A. By generating a change request and having it approved through the Perform Integrated Change Control process.B. This is typically done by using a version control system. The project manager creates a new version with the
PMP Exam Set A – Q56
Sometimes the broader, more comprehensive summary activity is also referred to as: A. Critical ActivityB. Hammock ActivityC. MilestoneD. Group Task Show Answer B. Hammock Activity
PMP Exam Set A – Q55
You are planning out the communications methods to use as part of stakeholder engagement. The most effective means for communicating and resolving issues with stakeholders is: A. Status reports.B. Electronic mail.C. Telephone calls.D. Face-to-face meetings Show Answer D. Face-to-face meetings
PMP Exam Set A – Q54
All of the following are tools of the Control Schedule process EXCEPT: A. Parametric estimatingB. Modeling techniquesC. Schedule compressionD. Leads and lags Show Answer A. Parametric estimating
PMP Exam Set A – Q53
Terry is managing a healthcare software development project using state-of-the-art technology. Stakeholder management is very crucial for the success of this project. The stakeholder involvement and influence is significant on this project. During which of following project stages, stakeholder management will be the most challenging task for Terry? A. Early during the project executionB. Towards