PMP Exam Set A – Q61

The Project Managers have maximum authority in which type of organization? A. Weak MatrixB. Strong MatrixC. FunctionalD. Balanced Matrix Show Answer B. Strong Matrix

PMP Exam Set A – Q60

John has just been assigned as the project manager of a project to develop a complex product. The project is in the Define Scope phase. Which of these tools / techniques will not be used by John in this phase? A. Lateral thinkingB. Process analysisC. Product breakdownD. Value engineering Show Answer B. Process analysis

PMP Exam Set A – Q59

Collect Requirements, Develop Schedule and Perform Qualitative Risk Analysis are all part of what process group? A. PlanningB. Scope PlanningC. Monitor and ControllingD. Executing Show Answer A. Planning

PMP Exam Set A – Q58

Which strategy attempts to reduce the probability and/or the impact of a risk to the point where the risk can be accepted? A. MitigationB. AvoidanceC. AcceptanceD. Transfer Show Answer A. Mitigation

PMP Exam Set A – Q57

How can changes be made to a project management plan once it has been baselined by the project manager? A. By generating a change request and having it approved through the Perform Integrated Change Control process.B. This is typically done by using a version control system. The project manager creates a new version with the

PMP Exam Set A – Q56

Sometimes the broader, more comprehensive summary activity is also referred to as: A. Critical ActivityB. Hammock ActivityC. MilestoneD. Group Task Show Answer B. Hammock Activity

PMP Exam Set A – Q55

You are planning out the communications methods to use as part of stakeholder engagement. The most effective means for communicating and resolving issues with stakeholders is: A. Status reports.B. Electronic mail.C. Telephone calls.D. Face-to-face meetings Show Answer D. Face-to-face meetings

PMP Exam Set A – Q54

All of the following are tools of the Control Schedule process EXCEPT: A. Parametric estimatingB. Modeling techniquesC. Schedule compressionD. Leads and lags Show Answer A. Parametric estimating

PMP Exam Set A – Q53

Terry is managing a healthcare software development project using state-of-the-art technology. Stakeholder management is very crucial for the success of this project. The stakeholder involvement and influence is significant on this project. During which of following project stages, stakeholder management will be the most challenging task for Terry? A. Early during the project executionB. Towards