PMP Exam Set A – Q52

A software vendor on your project is hoping to be awarded a contract providing software for another project at your company. You are not the manager of the other project. However, the vendor offers you tickets to an upcoming professional sports event if you will “put in a good word” for his company to vendor

PMP Exam Set A – Q51

Which of these precedence relationships is least commonly used in Precedence Diagramming Method? A. Start to StartB. Finish to FinishC. Finish to StartD. Start to Finish Show Answer D. Start to Finish

PMP Exam Set A – Q50

The requirements elicitation team has obtained a large number of ideas during sessions to gather product and project requirements. Which of the following techniques is best suited to have these ideas sorted into groups for review and analysis? A. Control chartB. Venn diagramC. Affinity diagramD. Brainstorming Show Answer C. Affinity diagram

PMP Exam Set A – Q49

The costs on a project are typically classified as direct and indirect costs. The cost of electric utilities for the office would be considered as: A. An indirect costB. Appraisal costC. A specific costD. A direct cost Show Answer A. An indirect cost

PMP Exam Set A – Q48

Project costs are estimated for all project activities and aggregated to establish a cost baseline. Which of the following statements about the cost baseline is NOT true? A. The project cost performance is measured against the cost baselineB. The cost baseline is an output of the determine budget processC. The cost baseline includes all authorized

PMP Exam Set A – Q47

You are the Project Manager for KT’s Lumber Yard. You are trying to forecast estimates for the last phase of the project you are currently working on. Based on the performance of the project to date, which formula can be used to estimate the total value of the project when completed assuming similar variances will

PMP Exam Set A – Q46

All of the following are characteristics of a project, EXCEPT: A. Has a definite beginning and endB. TemporaryC. Progressively elaboratedD. Ongoing Effort Show Answer D. Ongoing Effort

PMP Exam Set A – Q45 ( PMBOK 6th edition )

Gary is a project manager wrapping up the construction of a new office building. He creates several documents during this process. Which of the following is not applicable to the Control Procurements process? A. Lessons learned documentationB. Formal written notice of acceptance of deliverablesC. Closed contractsD. Project charter Show Answer D. Project charter

PMP Exam Set A – Q44

While the five process groups are typically completed in order, they often overlap with each other throughout the project. Which two process groups do not overlap unless a project is canceled? A. Initiating and ClosingB. Initiating and ExecutingC. Initiating and Monitoring and ControlD. Planning and Closing Show Answer A. Initiating and Closing

PMP Exam Set A – Q43 ( PMBOK 6th edition )

A project team is participating in a brainstorming meeting for a project. The project is in the planning phase. The team is trying to determine the current and preferred project stakeholder engagement levels and analyzing the gaps between these two states. They are also discussing different approaches and strategies that can be adopted to close