PMP Exam Set F – Q12

You are working with your customers on completed deliverables in your electronic parts manufacturing project. Since these parts are exported to other countries, they need more testing before your customers accept them. In this scenario, which of the following statements about the completed deliverables is CORRECT? A. Completed deliverables not accepted by customers must be

PMP Exam Set F – Q11

During the Control Scope phase, analysis of the scope performance resulted in a change request to the scope baseline. This change request will be processed for review and disposition in the: A. Control Quality phaseB. Perform Integrated Change Control phaseC. Monitor and Control Project Work phaseD. Validate Scope phase Show Answer B. Perform Integrated Change

PMP Exam Set F – Q8

A project team has recently computed the project’s current schedule and cost performance indices. They have also calculated the new estimate to complete and the TCPI based on the new estimate at completion. The project key stakeholders are not fully aware of the earned value management process. These measures in this case are an example

PMP Exam Set F – Q7

The project management team performed activities such as measuring examining and verifying to determine whether work and deliverables met requirements and product acceptance criteria. Which of the following choices refers to a different set of activities than the ones just mentioned? A. WalkthroughsB. PreventionC. InspectionD. Reviews Show Answer B. Prevention

PMP Exam Set F – Q6

In general, Perform Qualitative Risk Analysis is: _____________. A. not often completedB. complete and 100% accurateC. in-depth and thoroughD. quick and cost-effective Show Answer D. quick and cost-effective

PMP Exam Set F – Q4 ( PMBOK 6th edition )

A key output of Plan Resource Management is a list of project roles and responsibilities. What should this document include? A. Work packages, Effort, Authority, DutiesB. Role, Responsibility, Authority, RiskC. Role, Title, Resource Cost, ResponsibilityD. Role, Authority, Responsibility, Competency Show Answer D. Role, Authority, Responsibility, Competency