Sam, a senior project manager, is using a lessons learned knowledge management system to document the findings in a precision instrument manufacturing project. He is using the information from his team which has identified causes of product quality variance using a control chart and the details regarding corrective actions chosen to reduce the variance and
PMP Exam Set B – Q11
As part of the Estimate Costs process, a project manager obtained access to certain commercially available databases to get resource cost rate information. What type of input is such published commercial information considered as? A. Enterprise environmental factorB. Historical informationC. Organizational process assetD. HR Input Show Answer A. Enterprise environmental factor
PMP Exam Set B – Q10
At the end of a project, what will your schedule variance be equal to? A. ZeroB. Equal to the total PVC. OneD. Equal to the total EV Show Answer A. Zero
PMP Exam Set B – Q9
Your project is nearing completion, but a previously unidentified risk has been discovered and it could significantly affect one of the project deliverables. What do you do? A. Transfer the risk.B. Develop a risk mitigation plan.C. Include the issue in the project risk log.D. Notify the project stakeholders immediately. Show Answer D. Notify the project
PMP Exam Set B – Q8
A technique which enhances brainstorming with a voting process used to rank the most useful ideas so that they can be taken up for further brainstorming is: A. Six thinking hatsB. Nominal group techniqueC. Affinity diagramD. Mind mapping Show Answer B. Nominal group technique
PMP Exam Set B – Q7
You are on the vendor selection committee for a large IT project that you will be managing for your company. Your friend works for a company that is planning to bid on the project. During a social dinner, the friend tells his job is on the line if his company does not win the contract.
PMP Exam Set B – Q6
Your project sponsor has asked you to add 30% contingency to your project budget as a hedge against any unforeseen costs that could exceed the currently forecasted expenses, but has not provided any additional detail about why this is required. What do you do? A. Add 30% to the management reserves.B. Ask the sponsor to
PMP Exam Set B – Q5
Which of the following is not an activity related to the Direct and Manage Project Work process? A. Inspect the project deliverables for completeness.B. Provide, train, and manage the team members assigned to the project.C. Create project deliverables to meet the planned project work.D. Perform activities to accomplish project objectives. Show Answer A. Inspect the
PMP Exam Set B – Q4
Where would you find a detailed list and description of specific project assumptions associated with the project? A. Project charterB. Project scope statementC. Project configuration documentD. Change management plan Show Answer B. Project scope statement
PMP Exam Set B – Q3 ( PMBOK 6th edition )
In order to keep costs low, a project management team decided to apply statistical sampling while inspecting some of the work products. They decided to select 10 out of 50 engineering drawings for inspection. During which process should the sample frequency and sample size be determined? A. Collect RequirementsB. Plan Quality ManagementC. Control QualityD. Manage