What is the free float for Activity C? A. 4 daysB. 5 daysC. 6 daysD. 7 days Show Answer C. 6 days
PMP Exam Set B – Q1
Your project team members have just started to work together and are now adjusting their work habits and behaviors to support each other. Which stage of the Tuckman ladder has your team just entered? A. NormingB. PerformingC. FormingD. Storming Show Answer A. Norming
PMP Exam Set A – Q100
A project is contracted as a Cost-Plus-Fixed-Fee (CPFF) type of contract with a fee of 10% of estimated costs. The estimated cost is US$ 50,000. If the project comes in at US$ 75,000 with no changes in project scope, what would be the total cost of the contract? A. US$ 55,000B. US$ 125,000C. US$ 75,000D.
PMP Exam Set A – Q99
Select the best answer: Continuous process improvement reduces ___________ and ___________ , which allows processes to operate at increased levels of efficiency and effectiveness. A. Process and policy overhead.B. Departmental and organization processesC. Cost and scopeD. Waste and non-value added activities. Show Answer D. Waste and non-value added activities.
PMP Exam Set A – Q98 ( PMBOK 6th edition )
Jane has recently finalized her project management plan and has also got it approved. She is managing a complex manufacturing process improvement project. The project stakeholders’ continuous support and commitment is an absolute must for the success of the project. Which of the following are the most crucial stakeholder management processes at this stage? A.
PMP Exam Set A – Q97
A team of engineers is reviewing a scatter diagram to determine how the changes in two variables in a new type of automobile tire are related. The closer points on the diagram are to a diagonal line, ______________ . A. the more likely a control group will be requiredB. the more closely they are relatedC.
PMP Exam Set A – Q96
Two of your team members played the Mega Millions lottery and won! As much as they like working on your team, they have decided to retire. What plan should be updated? A. Retirement PlanB. Resource Availability DocumentC. Communications PlanD. Staffing Management Plan Show Answer D. Staffing Management Plan
PMP Exam Set A – Q95
A key project in an organization has been ignored due to high travel expenses associated with the movement of subject matter experts and other specialists across various project locations. Which of the following will permit such a project to be taken up in a cost-efficient manner? A. Management sign-offB. NegotiationC. Virtual teamsD. Co-location Show Answer
PMP Exam Set A – Q94
A project manager determines that there are 15 communication channels in the project. The number of stakeholders in the project must then be: A. 15 stakeholdersB. 6 stakeholdersC. 8 stakeholdersD. 105 stakeholders Show Answer B. 6 stakeholders
PMP Exam Set A – Q93
As an experienced PMP, you have found that running a WBS meeting is tricky because you need to find a balance between decomposition and excessive decomposition. When items are excessively decomposed it leads all of the following, EXCEPT: A. It breaks the 100% rule.B. Inefficient use of resourcesC. Non productive management effortD. Decreased efficiency when