PMP Exam Set G – Q11

You are an expatriate working in a foreign country and have been asked to offer a cash payment gift to the procurement manager at a company you are bidding on work for. How BEST should you interpret this request? A. Agree to provide the cash payment because the procurement manager controls whether your bid is

PMP Exam Set G – Q10

You are in the midst of a major code roll out for a new software module. However, it has come to your attention that the resources promised for the roll out are not going to be available. As the Project Manager, what is the BEST thing to do? A. Explain the impact of the lost

PMP Exam Set G – Q7 ( PMBOK 6th edition )

You have your project team members record the time they spend on different activities during the day such as: programming, electrical, HVAC, etc. This is an example of a tool and technique in what process? A. Manage CommunicationsB. Direct and Manage Project WorkC. Monitor and Control Project WorkD. Manage Team Show Answer C. Monitor and

PMP Exam Set G – Q6

Which process group corresponds to the “do” part of the plan-do-check-act cycle? A. ClosingB. Monitoring and ControllingC. PlanningD. Executing Show Answer D. Executing

PMP Exam Set G – Q3

A group of people were discussing multiple alternatives during the Collect Requirements process. One of the individuals in the group made the decision for the group. This method of reaching a group decision would be termed as: A. One Thinking HatB. DictatorshipC. PluralityD. Autonomy Show Answer B. Dictatorship