John, a project manager, for Code Crashers Inc. has been assigned a project where he must lead a group of inexperienced programmers in developing a software package that creates Material Safety Data Sheets (MSDS) for a chemical company. This is very similar to a project that his colleague, Peter, worked on in 2006, with some
PMP Exam Set G – Q11
You are an expatriate working in a foreign country and have been asked to offer a cash payment gift to the procurement manager at a company you are bidding on work for. How BEST should you interpret this request? A. Agree to provide the cash payment because the procurement manager controls whether your bid is
PMP Exam Set G – Q10
You are in the midst of a major code roll out for a new software module. However, it has come to your attention that the resources promised for the roll out are not going to be available. As the Project Manager, what is the BEST thing to do? A. Explain the impact of the lost
PMP Exam Set G – Q9 ( PMBOK 6th edition )
While analyzing the risks in a project, a project manager came up with a Risk Urgency Assessment document. In which process would this be done? A. Close RisksB. Monitor RisksC. Perform Qualitative Risk AnalysisD. Plan Risk Management Show Answer C. Perform Qualitative Risk Analysis
PMP Exam Set G – Q8
Which of the following may help in ensuring that certain bidders in the procurement process do not receive preferential treatment that all prospective sellers have a clear and common understanding of the procurement? A. Use of weighted criteriaB. Use of bidder conferencesC. Use of screening techniquesD. Use of expert judgement Show Answer B. Use of
PMP Exam Set G – Q7 ( PMBOK 6th edition )
You have your project team members record the time they spend on different activities during the day such as: programming, electrical, HVAC, etc. This is an example of a tool and technique in what process? A. Manage CommunicationsB. Direct and Manage Project WorkC. Monitor and Control Project WorkD. Manage Team Show Answer C. Monitor and
PMP Exam Set G – Q6
Which process group corresponds to the “do” part of the plan-do-check-act cycle? A. ClosingB. Monitoring and ControllingC. PlanningD. Executing Show Answer D. Executing
PMP Exam Set G – Q5
You are managing a heavy equipment manufacturing project that involves many mechanical, electrical as well as IT staff. Your team prepared a schedule network diagram using duration estimates with dependencies and constraints. Your team also calculated the critical path for the project using late and early values. Today, your project office has indicated about the
PMP Exam Set G – Q4 ( PMBOK 6th edition )
Emily is the project manager of a project that involves a buyer-seller relationship. The source selection criteria is an input to which of the following processes? A. Acquire ResourcesB. Conduct ProcurementsC. Control ProcurementsD. Plan Procurement Management Show Answer B. Conduct Procurements
PMP Exam Set G – Q3
A group of people were discussing multiple alternatives during the Collect Requirements process. One of the individuals in the group made the decision for the group. This method of reaching a group decision would be termed as: A. One Thinking HatB. DictatorshipC. PluralityD. Autonomy Show Answer B. Dictatorship