PMP Exam Set D – Q1

John is the project documents controller for a multi-million dollar telecom network deployment project. John has just received a document from the project manager. This document contains the project stakeholders’ communication requirements for the current project phase. John should update which of the following project documents with this information?

A. Work breakdown structure
B. Stakeholders engagement assessment matrix
C. Stakeholder management plan
D. Stakeholder register

C. Stakeholder management plan

PMP Exam Set C – Q100

You are the Project Manager of a large IT project. A manager from a company contracted to work on the project offers you free tickets to a local sporting event. The tickets are expensive but your organization has no formal policy regarding gifts. What is the BEST way to handle the offer?

A. Refuse the tickets and report the offer to your employer.
B. Accept the tickets but notify your employer.
C. Politely refuse the tickets.
D. Accept the tickets since there is no policy.

C. Politely refuse the tickets.

PMP Exam Set C – Q99 ( PMBOK 6th edition )

A project team is currently planning to perform the Monitor Stakeholder Engagement process to reassess the project stakeholders’ current engagement levels and review the current stakeholder management strategy. Which of the following is an output of this process?

A. Project documents updates
B. Information management system
C. Work performance data
D. Approved change requests

A. Project documents updates

PMP Exam Set C – Q98

Quantitative risk analysis should be performed:

A. only on risks identified by the project manager
B. only in extreme cases
C. only on prioritized risks
D. on all risks

C. only on prioritized risks

PMP Exam Set C – Q97

A project manager is informed that a limited number of resources are going to be available for his project. He creates a project schedule by adding buffers to the project to protect the target finish date. What type of schedule network analysis is he using?

A. What-if analysis
B. Critical path method
C. Critical chain method
D. Resource leveling.

C. Critical chain method

PMP Exam Set C – Q96

You are the Project Manager for Commodities, Inc. You are involved in a new project to create an internal web site for the employees of Commodities, Inc that will allow them to view events within the company. All of the following options listed are project constraints EXCEPT?

A. The project must be completed by December 31st of the current year.
B. There is a budget of $75,000 for the project.
C. The navigation menu for the website must be on the top of the page.
D. Only 3 employees are available to work on the project.

C. The navigation menu for the website must be on the top of the page.

PMP Exam Set C – Q95

Project performance measurements are used to assess the magnitude of variation from the original scope baseline. Once the degree of scope variation is known, what step is performed next?

A. Audit the project team
B. Upgrade the configuration management database with new controls.
C. Replanning
D. Root cause analysis of the cause of the variance relative to the scope baseline.

D. Root cause analysis of the cause of the variance relative to the scope baseline.

PMP Exam Set C – Q94

You are the Project Manager for Motor Cars, Corp. You are working on a project for the Human Resources department that is scheduled to take one year. After three months into the project, you calculate the EV at $35,000 and the PV at $45,000. Which option below represents the value for the SV?

A. -$10,000
B. 1.29
C. 0.78
D. $10,000

A. -$10,000

PMP Exam Set C – Q92

If you want to have multiple vendors bid on your contract, what is the best way to ensure that all vendors have the same information before bidding?

A. Issue a standard request for bid and do not allow any questions
B. Hold a bidder conference
C. Communicate only through email
D. Develop a qualified sellers list

B. Hold a bidder conference